Daily Service Report Archives

Wednesday, July 4, 2012

7:14 a.m. A Glenmont-bound Red Line train at Twinbrook was delayed 5 minutes due to debris on the track.

9:26 a.m. A Shady Grove-bound Red Line train at Rhode Island Avenue was offloaded due to a brake problem. Customers experienced an 8-minute delay.

9:45 a.m. A Franconia-Springfield-bound Blue Line train at Pentagon was delayed 4 minutes due to a signal problem.

10:22 a.m. A Vienna-bound Orange Line train at Stadium Armory was offloaded due to a brake problem. Customers experienced a 6-minute delay.

11:18 a.m. A New Carrollton-bound Orange Line train at Vienna did not operate, resulting in a 6-minute gap in service.

12:11 p.m. A New Carrollton-bound Orange Line train at Virginia Square was offloaded due to a brake problem. Customers experienced a 7-minute delay.

12:55 p.m. A Huntington-bound Yellow Line train at Eisenhower Avenue was offloaded due to a brake problem. Customers experienced an 18-minute delay.

2:16 p.m. A New Carrollton-bound Orange Line train at West Falls Church did not operate, resulting in a 6-minute gap in service.

2:17 p.m. A Huntington-bound Yellow Line train at Mt. Vernon Square was delayed 5 minutes due to an operational problem.

3:40 p.m. A New Carrollton-bound Orange Line train at Vienna did not operate, resulting in a 5-minute gap in service.

3:50 pm. A Silver Spring-bound Red Line train at Rockville was offloaded due to an operational problem. Customers experienced an 11-minute delay.

4:07 p.m. A Shady Grove-bound Red Line train at Grosvenor was offloaded and turned back for schedule adherence/improved train spacing.

4:13 p.m. A Branch Avenue-bound Green Line train at Greenbelt was delayed 7 minutes due to a signal problem.

4:40 p.m. A Silver Spring-bound Red Line train at Dupont Circle was offloaded due to a brake problem. Customers experienced a 9-minute delay.

5:10 p.m. A Largo Town Center-bound Blue Line train at Potomac Avenue was offloaded due to a door problem. Customers experienced a 9-minute delay.

5:26 p.m. A New Carrollton-bound Orange Line train at Court House was offloaded due to a brake problem. Customers experienced a 7-minute delay.

5:40 p.m. A Branch Avenue-bound Green Line train at Greenbelt was delayed 6 minutes due to a door problem.

6:02 p.m. A Silver Spring-bound Red Line train at Rhode Island Avenue was offloaded due to a brake problem. Several trains were single tracked around the incident train. Customers experienced 10-20 minute delays.

6:04 p.m. A Vienna-bound Orange Line train at New Carrollton did not operate, resulting in a 12-minute gap in service.

6:05 p.m. A New Carrollton-bound Orange Line train at West Falls Church did not operate, resulting in a 7-minute gap in service.

6:17 p.m. A New Carrollton-bound Orange Line train at West Falls Church did not operate, resulting in a 5-minute gap in service.

6:28 p.m. A Vienna-bound Orange Line train at New Carrollton did not operate, resulting in an 8-minute gap in service.

7:54 p.m. A Vienna-bound Orange Line train at Clarendon was offloaded and turned back for schedule adherence/improved train spacing.

8:19 p.m. A New Carrollton-bound Orange Line train at East Falls Church was offloaded due to a brake problem. Customers experienced a 12-minute delay.

9:44 p.m. A Largo Town Center-bound Blue Line train at Ronald Reagan Washington National Airport was delayed 20 minutes due to a signal problem.

10:11 p.m. A Vienna-bound Orange Line train at Ballston was offloaded due to a brake problem. Customers experienced a 9-minute delay.


Report Archives