Friday, December 5, 2014
5:28 a.m. A Greenbelt-bound Green Line train at Naylor road was offloaded due to an equipment problem. Passengers experienced a 12-minute delay.
6:21 a.m. A Branch Avenue-bound Green Line train at Greenbelt did not operate, resulting in a 6-minute gap in service.
6:23 a.m. A Glenmont-bound Red Line train at Tenleytown was offloaded due to a brake problem. Passengers experienced a 6-minute delay.
7:32 a.m. A Greenbelt-bound Yellow Line train at Van Dorn Street was offloaded due to an equipment problem. Passengers experienced a 12-minute delay.
7:49 a.m. A New Carrollton-bound Orange Line train at Vienna did not operate, resulting in a 4-minute gap in service.
8:04 a.m. A Huntington-bound Yellow Line train at Eisenhower Avenue was expressed for schedule adherence/improved train spacing.
8:31 a.m. A Branch Avenue-bound Green Line train at Navy Yard was delayed 4 minutes due to a medical emergency.
9:00 a.m. A Vienna-bound Orange Line train at Virginia Square was expressed for schedule adherence/improved train spacing.
10:00 a.m. A Largo Town Center-bound Blue Line train at Franconia-Springfield was delayed 9 minutes due to a brake problem.
10:03 a.m. A Franconia-Springfield-bound Blue Line train at Braddock Road was offloaded due to a brake problem. Passengers experienced an 8-minute delay.
10:13 a.m. A Fort Totten-bound Yellow Line train at Huntington was delayed 9 minutes due to an operational problem.
11:00 a.m. A Largo Town Center-bound Blue Line train at Potomac Avenue was expressed for schedule adherence/improved train spacing.
11:04 a.m. A Branch Avenue-bound Green Line train at Greenbelt was delayed 8 minutes due to an operational problem.
2:58 p.m. A Greenbelt-bound Green Line train at Prince George's Plaza was delayed 13 minutes due to a track problem.
3:01 p.m. A Franconia-Springfield-bound Yellow Line train at Greenbelt was delayed 9 minutes due to a track problem.
3:51 p.m. A New Carrollton-bound Orange Line train at East Falls Church was expressed for schedule adherence/improved train spacing.
4:59 p.m. A Branch Avenue-bound Green Line train at Shaw-Howard University was expressed for schedule adherence/improved train spacing.
5:16 p.m. A Greenbelt-bound Green Line train at Georgia Avenue-Petworth was expressed for schedule adherence/improved train spacing.
5:29 p.m. A New Carrollton-bound Orange Line train at Clarendon was expressed for schedule adherence/improved train spacing.
5:30 p.m. A New Carrollton-bound Orange Line train at Cheverly was expressed for schedule adherence/improved train spacing.
5:32 p.m. A Greenbelt-bound Green Line train at College Park was expressed for schedule adherence/improved train spacing.
8:00 p.m. A Glenmont-bound Red Line train at NoMa-Gallaudet was delayed 6 minutes due to a door problem.
9:13 p.m. A Fort Totten-bound Yellow Line train at Mt. Vernon Square was offloaded due to an equipment problem. Passengers experienced a 5-minute delay.
11:15 p.m. A Franconia-Springfield-bound Blue Line train at L'Enfant Plaza was offloaded due to a brake problem. Passengers experienced a 20-minute delay.
11:51 p.m. A Glenmont-bound Red Line train at Metro Center was delayed 4 minutes due to an unauthorized person on the track.