2019 Platform Improvement Project Highlights

Metro completed the first phase of the Platform Improvement Project in 2019, with six stations successfully reconstructed on the Blue and Yellow lines in Virginia. With all service closed south of Reagan National Airport during the summer, Metro provided shuttle bus service that successfully provided 26,000 trips per weekday. The stations reopened on time in September, and work continued with little impact to customers through the end of the year.  

To make sure you receive the latest 2020 project updates, including expected construction dates, locations and preliminary service, follow Metro on Twitter and Facebook or check back periodically at wmata.com/platformprogress.