Tuesday, October 9, 2012
7:02 a.m. A Mt. Vernon Sq-bound Yellow Line train at Huntington did not operate, resulting in a 6-minute gap in service.
8:29 a.m. A Glenmont-bound Red Line train at White Flint was offloaded due to a brake problem. Several trains were single tracked around the incident train. Customers experienced an 18-minute delay.
8:40 a.m. A Huntington-bound Yellow Line train at Mt. Vernon Square did not operate, resulting in a 6-minute gap in service.
9:21 a.m. A Largo Town Center-bound Blue Line train at Arlington Cemetery was expressed for schedule adherence/improved train spacing.
9:36 a.m. A Shady Grove-bound Red Line train at Van Ness was offloaded due to a door problem. Customers experienced a 6-minute delay.
11:41 a.m. A Silver Spring-bound Red Line train at Rockville was delayed 8 minutes due to a door problem.
3:13 p.m. A New Carrollton-bound Orange Line train at West Falls Church did not operate, resulting in a 6-minute gap in service.
3:26 p.m. A Greenbelt-bound Green Line train at Mt. Vernon was expressed for schedule adherence/improved train spacing.
3:51 p.m. A Branch Avenue-bound Green Line train at Naylor Road was expressed for schedule adherence/improved train spacing.
3:33 p.m. A Silver Spring-bound Red Line train at Farragut North was offloaded due to a brake problem. Customers experienced a 6-minute delay.
4:39 p.m. A Glenmont-bound Red Line train at Wheaton was offloaded due to a brake problem. Customers experienced a 4-minute delay.
4:44 p.m. A Glenmont-bound Red Line train at Woodley Park was offloaded due to a door problem. Customers experienced a 4-minute delay.
5:51 p.m. A Branch Avenue-bound Green Line train at Suitland was expressed for schedule adherence/improved train spacing.
5:59 p.m. A Silver Spring-bound Red Line train at Grosvenor was offloaded due to a brake problem. One train offloaded and turned back for schedule adherence/improved train spacing. Customers experienced a 16-minute delay.
6:52 p.m. A Branch Avenue-bound Green Line train at Prince George’s Plaza was offloaded due to a brake problem. Customers experienced a 12-minute delay.
9:07 p.m. A Branch Avenue-bound Green Line train at Congress Heights was offloaded due to a door problem. Customers experienced a 16-minute delay.
10:45 p.m. A Franconia-Springfield-bound Blue Line train at Van Dorn Street was offloaded due to a brake problem. Several trains were single tracked around the incident train. Customers experienced a 31-minute delay.