SafeTrack Progress reports

Surge Date Duration Lines Impact Area Affected
# 1 June 4 - 16 13 days Orange Line Silver Line Continuous Single Track East Falls Church to Ballston
Progress Report
# 2 June 18 - July 3 16 days Orange Line Blue Line Silver Line Line Segment Shutdown Eastern Market to Minnesota Ave & Benning Road
Progress Report
# 3 July 5 - 11
7 days Yellow Line Blue Line Line Segment Shutdown National Airport to Braddock Road
Progress Report
# 4 July 12 - 18 7 days Yellow Line Blue Line Line Segment Shutdown Pentagon City to National Airport
Progress Report
# 5 July 20 - 31 12 days Orange Line Silver Line Continuous Single Track East Falls Church to Ballston
Progress Report
# 6 August 1 - 7 7 days Red Line Continuous Single Track Takoma to Silver Spring
Progress Report
# 7 August 9 - 21 13 days Red Line Continuous Single Track; weekend line segment shutdown Shady Grove to Twinbrook
Progress Report
# 8 August 27 - September 11 16 days Yellow Line Blue Line Continuous Single Track; weekend line segment shutdown Franconia-Springfield to Van Dorn Street
Progress Report
# 9 September 15 - October 26 42 days Orange Line Continuous Single Track; weekend line segment shutdown Vienna to West Falls Church
Progress Report
#10 October 29 - November 22 25 days Red Line Line Segment Shutdown Fort Totten to NoMa
Progress Report
#11 November 28 - December 21 24 days Orange Line Silver Line Continuous Single Track East Falls Church to West Falls Church